Minutes from the planning and building officer's disposal meetings of 29 April 2009 and 6 May 2009 were presented.
Planning and Building Council
in the council chamber, Strandgata 6
Secretary
- Heiðbjört Guðjónsdóttir representative
-
General presentations
-
SB040377 – Minutes of the Planning and Building Officer
;Part A of the minutes is submitted to the town council for approval.
-
0902033 – Norðurbakki 5, change to the detailed plan
The proposal for an amendment to the detailed plan for Norðurbakki, concerning the access road, location and height of the substation and a nearby container, as shown on the drawing by Batteríið dated 29 January 2009, is reconsidered. The detailed plan has been advertised since 06.03.2009 in accordance with the 2nd paragraph of Article 26 of the Planning and Building Act no. 73/1997, with a comment period until 03.04.2009. Comments were received. A summary of the comments received was presented by the Planning and Building Department.
The Planning and Building Committee adopts the recommendation of the Planning and Building Department. The elevation of the upper edge of the substation roof will remain unchanged from the currently approved detailed plan. The refuse container will be located at the sewage pumping station on the North Shore, in accordance with the approved detailed plan. The Planning and Building Committee approves the application and that the matter will be finalised in accordance with Article 26 of the Planning and Building Act No. 73/1997.
-